Calender in Outlook

K

Keith Rigg

If you change the working week days to Monday, Tuesday, and Friday the view
for the Work Week is not displayed correctly.
 
M

Milly Staples [MVP - Outlook]

Please explain "Correctly" as it does in OUtlook 2000. I am not at home so I
can't verify Outlook 2002 or 2003. What version are you using?
 
K

Keith Rigg

Hi Milly,

Thanks for the reply - this is related to Outlook 2003 with or without
Service Pack 1 with an Exchange 2003 Enterprise Server.

When you change the working week (Tools, Options, Calender Options ) to say
Monday, Tuesday, Wednedsay and Thursday and click on the "(5) Work Week" the
calendar view changes and the display is correct for both this weeks view and
the monthly view with the Grey Shaded bar displays the correct four days.

If you now change the options to Monday, Tuesday and Friday the display
shows Monday, Tuesay and Wednesday. (Try changing it to Monday and
Friday.......)

I have tried this on several different machines and even tried updating mine
using office updates - but the problem is not fixed.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top