Hello Praful,
Welcome to the Project newsgroup. I'm afraid I don't fully
understand your question. You have created a calendar with all 7
days per week as working time. Have you set that calendar as
either:
- the Project calendar through Project > Project Information?
- the resource's base calendar on the Resource Sheet or Resource
Information?
- the task calendar through Task Information?
When you say you've calculated it as "5 days in actual as working
days" what do you mean? Do you have resources assigned to the task?
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project