CALENDER PROBLEM

P

Praful

Hi,
I facing a problem in MSP 2007, I created 7 days calender but it is showing
5 days in actual as a working days as i calculated it mannually.
 
J

JulieS

Hello Praful,

Welcome to the Project newsgroup. I'm afraid I don't fully
understand your question. You have created a calendar with all 7
days per week as working time. Have you set that calendar as
either:

- the Project calendar through Project > Project Information?
- the resource's base calendar on the Resource Sheet or Resource
Information?
- the task calendar through Task Information?

When you say you've calculated it as "5 days in actual as working
days" what do you mean? Do you have resources assigned to the task?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top