Dear All,

To set days in calender we use Change working time and adjust the
calender. If i want 6 days in a week as working days and 2 and 4th sat
should be non-working days in month.
while defining Hours per day will be 8hrs
but how to define hours per weak? and how to define days per month?

right now i am making 2 and 4th sat as non-working days. But this is
risky and time consuming to make it for all months in 4-5 years
project?

can any one can guide me on this. How i should define the calender?

Thanks in advance.

Nilu
 
M

Mike Glen

Hi Nilu,

Welcome to the Microsoft Project newsgroup :)

With these sort of variable hours, you will have to compromise. Remember
the definition of week and month is what Project uses if you enter a
duration of weeks or months. If you only enter hours, then your calendar
will prevail as you want it. You might like to see FAQ Item: 5. Default
Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top