Calender View Customization

S

Saadia

Hi,
Just started using MS Project a few weeks ago.
Currently in the calender view i can only see my tasks
and their duration. Is there a way to show the task and the resource
that will be working on that task. This way i would just
look at the calender and know who is assigned to a task and on what day.
Thanks
 
J

JulieS

Saadia said:
Hi,
Just started using MS Project a few weeks ago.
Currently in the calender view i can only see my tasks
and their duration. Is there a way to show the task and the resource
that will be working on that task. This way i would just
look at the calender and know who is assigned to a task and on what
day.
Thanks

Hello Saadia,

Choose Format > Bar Styles and select the non-critical bar style in the
list. Edit the field(s) area to say: Name, Duration, Resource, Resource
Names

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
S

Saadia

Thanks,
that helped a lot!
JulieS said:
Hello Saadia,

Choose Format > Bar Styles and select the non-critical bar style in the
list. Edit the field(s) area to say: Name, Duration, Resource, Resource
Names

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 