Tools > Change Working Time, copy the calendar and make a new one.
Either save the file as a template and use as the base for new projects or
open the the new project and this project at the same time. Open Tools >
Organizer, and use the Organizer interface to copy the calendar to the new
file.
You need to have it in the Global.mpt file. Do this via Tools/Organizer.../Calendars tab. Bottom right you should see your common calendar - select it and Copy to the left which should be showing Golbal.mpt.
How can set the common calender that can be assigned to numer of
projects?