We are using Project server 2003.
Can we prevent a task from starting due to inavailability of resources?
Within a project I can prevent a task from starting due to resource
inavailability by making that task dependent on another task assigned to the
same resource The first task can not start unless the resource has already
completed the second task.
I can do the same thing for projects that are related. But how about for
projects that are not related or projects handled by different PMs sharing
resources? Will the system inform the 1st PM that task A can not start yet
because his resource is not finish with Task B assigned by the 2nd PM?
These things can happen even if both PMs checked the availability of the
resources when preparing the project plans. One project may be ahead of
schedule or delayed thus the problem of resources.
THank you in advance for your answers.
Can we prevent a task from starting due to inavailability of resources?
Within a project I can prevent a task from starting due to resource
inavailability by making that task dependent on another task assigned to the
same resource The first task can not start unless the resource has already
completed the second task.
I can do the same thing for projects that are related. But how about for
projects that are not related or projects handled by different PMs sharing
resources? Will the system inform the 1st PM that task A can not start yet
because his resource is not finish with Task B assigned by the 2nd PM?
These things can happen even if both PMs checked the availability of the
resources when preparing the project plans. One project may be ahead of
schedule or delayed thus the problem of resources.
THank you in advance for your answers.