C Palmer
Hi all
I have a vacation macro that shows all the holidays that
my resources have.
I have my own project with a custom group on a table. what
i want to do is when the vacation macro is ran and i have
saved it and inserted it into my project, i want the tasks
for each individual resource to be placed under the
appropriate group. i tried doing this by sharing the
resources and adding them to the appropriate task but this
added more holidays to the bars, so i think this needs to
be done via the macro.
If anyone can help this would be much appreciated
Regard
C Palmer
I have a vacation macro that shows all the holidays that
my resources have.
I have my own project with a custom group on a table. what
i want to do is when the vacation macro is ran and i have
saved it and inserted it into my project, i want the tasks
for each individual resource to be placed under the
appropriate group. i tried doing this by sharing the
resources and adding them to the appropriate task but this
added more holidays to the bars, so i think this needs to
be done via the macro.
If anyone can help this would be much appreciated
Regard
C Palmer