T
TomL
We are using Server 2003, SP1. We use managed time periods, timesheets, and
report Hours worked and remaining work. We are trying to get EV working
correctly. Right now it looks like we have have to enter % complete manually
to get SPI and CPI to be calculated. I would prefer to let Project calculate
the % complete, instead of having to calculate it and enter it.
Any suggestions?
report Hours worked and remaining work. We are trying to get EV working
correctly. Right now it looks like we have have to enter % complete manually
to get SPI and CPI to be calculated. I would prefer to let Project calculate
the % complete, instead of having to calculate it and enter it.
Any suggestions?