Can I add a red line to show the current date over in PWA?

M

mrw0915

Just as I can do over in the project instance...I am trying to find out how
to add a red line to show the current date over on the PWA side. We like to
add this sort of line over in the Project instance to simply make it more
clear what the current day is, so we were wondering if we could do the same
thing over on the PWA side but have been unable to find out how to do that so
far...if it is even possible at all.

Anyway, just looking to see if anyone knows how to do that over in PWA or
just to somehow confirm if it is even possible or not.

Thanks!
 
D

Dale Howard [MVP]

mrw0915 --

It is not possible to display a current date line in any Project Center or
Project views in PWA. Sorry.
 
M

mrw0915

Thanks again Dale, that is what we thought...but just wanted to make sure
were weren't missing something.
 