Hello Soapman,
I agree that the Calendar view is helpful from a presentation stand
point to people who find Gantt charts baffling. However, the
Calendar view is not terribly useful when dealing with multiple
tasks (usually more than 4-5) which span the same time frame. What
I find useful for individual users is to filter a Calendar view
showing only tasks assigned to a particular resource. Then print
the view, re-filter for the next resource and repeat the process.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project