You can do it in Project but it seems like hunting flies with an elephant
gun to me. I have a task that will take 20 man-hours of work. I want to
complete it by Christmas, 7 weeks from now. I work on average 40 hours per
week, 8 hours per day. There are 35 working days, 280 working hours
between now and Christmas. Therefore I need to spend 20/35 hours per day or
something between 30 and 45 minutes a day working on it. That's exactly the
same calculation Project does but at this scale of complexity I don't need
hundreds of dollars worth of software to do it. At this level all you need
is a calendar, pencil, and scratch paper; a middle-tech solution would be
the Outlook calendar and Windows calculator; or you can go really high-tech
and use Excel.
If you do want to use Project anyway, perhaps so you get the pretty Gantt
chart pictures, you'd list yourself as a resource (the only resource?) in
the resource sheet and input the tasks and the durations within which you'd
like to complete them. Split the screen and mark the tasks fixed duration.
Assign yourself to the tasks as the resource working them. Enter the work
estimate for the task and Project will calculate the percentage of your
working time you'll need to devote to accomplish that much work within the
duration specified. To play with the date, switch the task type to fixed
work and when you edit duration Project will recalculate the effort, the
percentage of your time, accordingly. If you look at the resource sheet and
see your name listed in red, it means you've scheduled yourself for more
total work in a day than your calendar says you want to do overall.
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs