D
Damon
Does MS Project 2007 have the capabilities to input a start and finish time
for a specific task in conjunction with the Start and Finish dates?
Example:
Task 1-Excavate Dirt- Monday Oct 1. 07:00hrs to 12:00hrs
Task 2-Build forms- Monday Oct 1. 12:00hrs to 14:00hrs
Task 2-Form Rebar- Monday Oct1. 14:00hrs to 19:00hrs
etc.
Thanks in advance for your help
Damon
for a specific task in conjunction with the Start and Finish dates?
Example:
Task 1-Excavate Dirt- Monday Oct 1. 07:00hrs to 12:00hrs
Task 2-Build forms- Monday Oct 1. 12:00hrs to 14:00hrs
Task 2-Form Rebar- Monday Oct1. 14:00hrs to 19:00hrs
etc.
Thanks in advance for your help
Damon