J
Joe
I have a resource that I have split between three
different task items that run at the same time. For
planning purposes I allocated the task as follows.
Task A: 50%
Task B: 35%
Task C: 15%.
Lets assume this is one resource and all three tasks have
a duration of 2 weeks. So the allocations are
4 hours for task A
2.8 hours for task B
1.2 hours for task C.
This is the planned allocation of work for this resource.
When I get the actual hours for day 1, 2 and 3. Lets
assume the resource puts in
5 hours for task A
2.8 hours for task B
..2 hours for task C
for all three days.
Is there any way to keep task C (only) from not changing
the "planned" hours of work for the rest of the duration?
I ask this because task C is really a "Support Role"
task. The task does not have a set number of hours, I am
just reserving 1.2 hours for support functions, I only
want to allocate the 1.2 hours a day, regardless of how
much was used the previous day. For task A and B, I want
it to account for what has already been done, so I am okay
with how that works. It's just task C I want to have
fixed "work" no matter what the actual work done was. Is
there any way to do this?
different task items that run at the same time. For
planning purposes I allocated the task as follows.
Task A: 50%
Task B: 35%
Task C: 15%.
Lets assume this is one resource and all three tasks have
a duration of 2 weeks. So the allocations are
4 hours for task A
2.8 hours for task B
1.2 hours for task C.
This is the planned allocation of work for this resource.
When I get the actual hours for day 1, 2 and 3. Lets
assume the resource puts in
5 hours for task A
2.8 hours for task B
..2 hours for task C
for all three days.
Is there any way to keep task C (only) from not changing
the "planned" hours of work for the rest of the duration?
I ask this because task C is really a "Support Role"
task. The task does not have a set number of hours, I am
just reserving 1.2 hours for support functions, I only
want to allocate the 1.2 hours a day, regardless of how
much was used the previous day. For task A and B, I want
it to account for what has already been done, so I am okay
with how that works. It's just task C I want to have
fixed "work" no matter what the actual work done was. Is
there any way to do this?