Can I limit a resource's availability on one project?

T

Tricia R.

I have an enterprise resource who is available to projects 100% but I would
like to be able to control the availability in my particular project. In a
non-enterprise environment, you can do this by setting their availability
since it only applies to your project. Is there a way to do this at the
project level in the enterprise environment.
 
D

Dale Howard [MVP]

Tricia --

There is no way to change the availability for a resource in a particular
project and then "make it stick" after you save, close, and reopen the
project. What you can do this this, however:

1. Open the project in particular
2. Apply the Resource Sheet view
3. Set the Max. Units for each resource for this particular project
4. Apply the Gantt Chart view
5. Assign resources to tasks based on their temporary Max. Units values

After you save and close the project, the Max. Units value will return to
the value set in the Enterprise Resource Pool for these resources. Hope
this helps.
 