Can I make a Microsoft Project WITHOUT a Calendar?

E

Elizabeth

I just want to track percentages of completion only. No Timeline for
completion, because it is a project too ongoing that to set timelines makes
everything look like its at 2% when its at 80% for example.
I dont want the complication of timeline calendars PER task etc.. just Have
a 100% meter, and everything at its Percentages in relation to that
percentage.
I just want to disable any and all resource calendars, task calendars etc.
Thanks
 
E

Elizabeth

Is that because, you cant do it in Project or Excel is just easier to manage
that?

I dont think you can have tasks and dependent tasks though.
though I appreciate the quick response, without a reason why Excel is
preferred, I am inclined to wait for another response..
 
J

Jack Dahlgren

You can have dependent tasks through use of a simple formula.
From what you wrote it appeared that you did not want any starting and
finishing dates at all so there is no need for project.

If you need dates and dependencies, then project would be OK. There is no
need to have task or resource calendars other than the standard calendar. As
long as you do not create them then they won't exist.

-Jack
 
S

Steve House

You can't do it in Project - indeed, what you are asking for isn't a project
plan at all, just a to-do list. A project is defined as a time-limited
undertaking having observable starting and ending points that results in the
creation of a measurable and unique deliverable. Tasks are defined as the
observable physical work activities required to create that deliverable and
they too have clearly defined and observable start and end times. In
Project Management terms, until you have determined specific start and
finish times, you really don't have a task, just an objective. Project
planning software such as MS Project is a tool designed to create the
schedule for and manage the work required to achieve that undertaking. A
"schedule" implies that we are looking not only at WHAT work needs to be
performed but also WHEN it needs to be performed. Indeed, the whole purpose
that planning software such as MS Project has for existing is to create such
a plan so that you are able to schedule and manage the activities of a
number of resources down to the level of being able to tell a plumber that
he is to show up at the job-site on Tuesday ready to install a bathtub and
tell the painter that the plumber will be done and out of the way by
Wednesday so he can start painting that bathroom then.

No offense but your statement that "timelines make everything look like
they're 2% when they're really 80%" also reflects a fundamental conceptual
error. % Complete is defined as the duration of a task that has passed
since it actually began compared to the total duration required to complete
the task. It is a measure of the passage of time where work has actually
been done. The project, or a task within it, cannot be 80% done when 2% of
its required time has passed by because "% Done" is "% of Required Time That
Has Been Worked" by definition and 80<>2.

Hope this helps
 
J

Jan De Messemaeker

Hi Elisabeth,

There are no task calendars unless you make them; that's one problem solved.
You do not have to manage your resource calendars - they will just be a copy
of the project calendar, so why worry? Another problem solved.
But you will be "stuck" with a project calendar - but if you don't care,
just leave the default.

Then what else may be bothering you? The fact that Project shows start and
finish dates? Hide the columns.

But contrary to my fellow MVP's I advise you NOT to shift to Excel because:
- Managing dependencies is NOT a mattzer of "simple formulas" it is a very
complex logic, way too complex to seriously do with Excel formulas.
- I'm completely convinced that once you lose your fear for the p roduct,
you will ask more of project - why not look at forecasted finishing dates
(isn't that project Management elementary), why not introduce holidays in
your calendar...

You'll be happy to have gone on with the right product.

Greetings,
 
A

Aggiengr

I am trying to do the same basic thing. Mine is for calculating man-hours
for a manufacturing process. I don't have a specific start DATE, just amount
of time it takes for specific tasks. I have a heirarchy of dependencies
which will drive parallel/serial processing. But, Projects keeps throwing in
calendars.
 
J

Jan De Messemaeker

Hi,

Sorry that is NOT true.
Project doesn't "throw in calendars"
It spontaneously uses one calendar, the project calendar, ONE.
All the others if any are created and introduced by YOU not "thrown in" by
Project.
Greetings,
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top