Can I see task notes or comments in Project center?

  • Thread starter åŠæ–°ä¸æ—§
  • Start date
Å

åŠæ–°ä¸æ—§

Hi, I am with PS2007+PWA. Currently, only resources with assignments can see
task notes for their own tasks through PWA_My Tasks page; and PM can see the
notes from project professional.
How can I present all tasks notes on PWA_Project Center_Project Detail or
somewhereelse, so that every one could find interested information?

Thanks in advance,

JJin
 
D

Dale Howard [MVP]

JJin --

You can add the Notes field to any Project Center view or detailed Project
view, however, in either situation the system limits the number of
characters that display in the Notes field. I think you have probably
already discovered this limitation by now. I know of no way around this
limitation. Sorry.
 
Å

åŠæ–°ä¸æ—§

Thank you, Dale. This should be the way... However, seems it taking very long
time to load the grids. For my 60 lines project which 30 tasks attached
notes, the project detail view froze few minutes to load in the data, and did
not succeed. Once I remove "notes" field from that view, loading grid becomes
very efficient.

My most concern is to show transaction details (who made progress on what
time and its comments) to all project team members. Do you have any
suggestion on this request?

Thanks in advance,

JJin
 
D

Dale Howard [MVP]

JJin --

I know of no default way to accomplish this in Project Server 2007. Sorry.
 