A
AlaskaRae
I'm trying to map out a project. Some of the work is completed in Anchorage,
using regular office hours (standard). Another portion of the work is
completed on the North Slope in the oil field. A work day for these fellows
is from 6:00 am - 6:00 pm with a 30 minute lunch 7 days a week. If I use
standard working times 8-5 then it shortens the duration of my project. If I
use the "Slope's" working times, then I get strange decimals all over the
place. Help?
using regular office hours (standard). Another portion of the work is
completed on the North Slope in the oil field. A work day for these fellows
is from 6:00 am - 6:00 pm with a 30 minute lunch 7 days a week. If I use
standard working times 8-5 then it shortens the duration of my project. If I
use the "Slope's" working times, then I get strange decimals all over the
place. Help?