Can I show summary durations as weeks in MS Project 2002

M

megannwv

I am creating a long duration project and entering task durations as weeks.
However my Summary Tasks still show as days, can I change this to show them
as weeks.
 
J

Jan De Messemaeker

Hi,

Tools, Options, Schedule, Durations are entered as ... select Weeks
HTH
 
B

Bob S.

Is there any way to get task durations to seconds or even tenths of seconds.
I think this could be a great tool for industrial time study work if I could
get the durations shorter
 