I am working on a project which a same group of tasks will be concurrently
happened in several cities. I created a project plan that tasks grouped by
city(I put city's name as a summary task) and assign 4 city's job to 1
resource.
On <PWA-My Assignments> view, resources can see all their tasks under this
Project Name, but can not see the Summary Task level. I even tried to insert
a Text1 field on my assignments view and group tasks by this attribute,
however the data entered in <Project_Professional - column text1> are not
published to this field in PWA.
Question:
1- How can I present tasks by 3 level as <Project Name> - <Summary Task
Name> - <Task Name>?
2- Is it true that some attributes in professional will not be published to
PWA?
Thanks in advance,
JJin
happened in several cities. I created a project plan that tasks grouped by
city(I put city's name as a summary task) and assign 4 city's job to 1
resource.
On <PWA-My Assignments> view, resources can see all their tasks under this
Project Name, but can not see the Summary Task level. I even tried to insert
a Text1 field on my assignments view and group tasks by this attribute,
however the data entered in <Project_Professional - column text1> are not
published to this field in PWA.
Question:
1- How can I present tasks by 3 level as <Project Name> - <Summary Task
Name> - <Task Name>?
2- Is it true that some attributes in professional will not be published to
PWA?
Thanks in advance,
JJin