Can I Track Changes in Subprojects/Master?

M

mike c

Hi All,
I'm trying to set up a Master Schedule, using subprojects of course. My
question is, is there any way to track changes that have occurred in the
subprojects. For example if our client updates or changes their subproject
in some way, how will I see these changes in the Master? (well besides doing
a line by line comparison... with an earlier version?) Is there an easy way
to Track Changes like MS Excel? Or a way to receive updates of any changes
made in the subprojects? thanks in advance
 
M

mike c

Hi Jack, thaks for the reply, I'll have a look, i failed to mention i have
project 2000, but there is a similiar update.
 