D
Danny
I have tasks with multiple generic resources, and even a single generic
resource, that spans across months. We are in a fixed duration mode,
non-effort driven task type. My project leads give me "work" hours per month
and that is how it is transferred out to another software program. If I just
enter the total hours in the Gantt chart view, the hours are contoured per
the selected contour. There is no contour that seems to fit the monthly
spread that I am given. Is it possible to use the Resource Usage/Work Table
View to enter the monthly hours on the tasks? Is there a potential problem if
I do this?
resource, that spans across months. We are in a fixed duration mode,
non-effort driven task type. My project leads give me "work" hours per month
and that is how it is transferred out to another software program. If I just
enter the total hours in the Gantt chart view, the hours are contoured per
the selected contour. There is no contour that seems to fit the monthly
spread that I am given. Is it possible to use the Resource Usage/Work Table
View to enter the monthly hours on the tasks? Is there a potential problem if
I do this?