Can My Tasks show a different week than the timesheet period?

R

rebecca

We have a business rule that dictates a Saturday - Friday timesheet
period.

The only problem is, PWA 2007 looks at the Saturday date and gives the
user the associated week.

Thus, every time my users want to enter their time for the current
week, they have to push the "previous" button.

Little problem, big grief! Can the view look different from the
timesheet period?

thanks!
 
D

Dale Howard [MVP]

Rebecca --

Did your Project Server administrator specify Saturday as the Week Starts On
option in PWA? Ask him/her to do the following:

1. Log into PWA with administrator permissions.
2. Click Server Settings - Task Settings and Display.
3. In the Reporting Display section, click the Week Starts On pick list and
choose Saturday.
4. Click the Save button.

Let us know if this helps.
 