Immeidately after an upgrade of Server 2007 to SP2, users could no longer
edit actual hours in My Task's daily time grid, but could still edit other
fields like “Start†and “Finish". We figured the February 2010 Cumulative
Update (CU) would fix it.
We tried switching and testing all three tracking methods (Percent work
complete, Actual work done and work remaining, Hours or work done per
period). Still, we can not enter time under each date. Also tried
republishing the project and that didn’t fix it either.
Any ideas? Is this a known problems in Feb CU? should we try December or
April 2010? Or do you think it is something completely different?
/Spiro Theopoulos
Immeidately after an upgrade of Server 2007 to SP2, users could no longer
edit actual hours in My Task's daily time grid, but could still edit other
fields like “Start†and “Finish". We figured the February 2010 Cumulative
Update (CU) would fix it.
We tried switching and testing all three tracking methods (Percent work
complete, Actual work done and work remaining, Hours or work done per
period). Still, we can not enter time under each date. Also tried
republishing the project and that didn’t fix it either.
Any ideas? Is this a known problems in Feb CU? should we try December or
April 2010? Or do you think it is something completely different?
/Spiro Theopoulos