Can not view task cost information

H

Henry

Hi,
I wrote a PDS extender to create a project with several
tasks. Eech task has fixed cost, cost, remaining cost
information. The PDS published the project plan to the
server. The web access can display the tasks' start and
finish time information. However, it can not display task
costs information.

To create the project (tasks), I added rows in tables
MSP_PROJECT, MSP_TASKS, MSP_WEB_PROJECT,
MSP_WEB_ASSIGNMENTS. Do I need to update other tables in
order to display the cost information?

Thanks,

Henry.
 