J
jose
Hello All,
I'm not sure if this is the correct group to post to but I had a
solver question. I have been looking at the Solver tool briefly, and
have also viewed some Sample spreadsheets that showed its
capabilities. I was wondering if it could handle something like the
following:
A construction company currently has four large jobs, and each job
needs dirt hauled to it (a lot of dirt). They have three different
sizes of trucks, each costing different amounts of money. Also, time
is an important factor and these jobs need to be done in the quickest
amount of time. So... if I entered:
1.The amount of dirt needed at each job, as well as the round trip
time to each job site
2.The number of each truck available (lets say there are only fifteen
trucks in total available - Consisting of the three types), and the
cost of each unit
3.How much each unit could haul
Could solver give me an answer showing how many of each truck I need
for each job site to give me the cheapest and fastest method to haul
the material? For some reason, I believe that there are too many
constraints for solver but I am not too sure. If anyone thinks this
could work, or knows of a different program that would work, could you
please let me know. Any help would be greatly appreciated.
Thanks In Advance,
Jose
I'm not sure if this is the correct group to post to but I had a
solver question. I have been looking at the Solver tool briefly, and
have also viewed some Sample spreadsheets that showed its
capabilities. I was wondering if it could handle something like the
following:
A construction company currently has four large jobs, and each job
needs dirt hauled to it (a lot of dirt). They have three different
sizes of trucks, each costing different amounts of money. Also, time
is an important factor and these jobs need to be done in the quickest
amount of time. So... if I entered:
1.The amount of dirt needed at each job, as well as the round trip
time to each job site
2.The number of each truck available (lets say there are only fifteen
trucks in total available - Consisting of the three types), and the
cost of each unit
3.How much each unit could haul
Could solver give me an answer showing how many of each truck I need
for each job site to give me the cheapest and fastest method to haul
the material? For some reason, I believe that there are too many
constraints for solver but I am not too sure. If anyone thinks this
could work, or knows of a different program that would work, could you
please let me know. Any help would be greatly appreciated.
Thanks In Advance,
Jose