Is it possible to show tasks more than once if they are relevant to more than
one workstream (group of tasks)? They should then ideally both (all) update
if updated in one place.
Thanks
Henrik
As others have pointed out, this is not a "normal" occurrence.
However, I have run across it when things are combined -- in my case,
combined progress reviews -- and continuity with previous schedules is
desired.
Consider two parts, each with their own tasks to completion. When it
becomes apparent that they will finish around the same time, it
becomes possible to have a single review meeting encompassing both
products. As such, I have renamed the two reviews, put a common set
of predecessors on one, and made the second a successor to the first.
(Links would work as well in theory, but I don't care for them.) The
customer desires to see it this way for continuity with previous
schedules, but I want to ensure the two dates are always the same.
1.0 Part 1
...
1.4 Combined Review - Part 1 & 2 (1.3 FS, 2.3 FS)
2.0 Part 2
...
2.4 Combined Review - Part 1 & 2 (1.4 SS)
One could use the same predecessors on both reviews, but that will be
double work if they need to be revised for some reason. The
successors to these reviews remain unchanged.
The alternative (normal?) tact is to move the review "out" one or more
levels and only have a single task. This will require adjusting all
the successors.
In either case, you will have some jiggering to do to sync up with
your baseline and EV if there is work associated with this task. On
the whole, I think keeping the task listed twice entails less editing
(and therefore potential for error).
Paul