Can we have access control within MS Project to view limited tasks

S

Satya

Hi,
Can we have access control within MPP (MSP 2002 or higher) to view limited
tasks?
Regards
Satya
 
J

JulieS

Hello Satya,

Sorry, no. If a user has the Project file s/he can open and view all fields
for all tasks. If you need to limit access, then print the view or views
with filters applied to show only selected tasks.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information about
Microsoft Project
 