J
Jinesh Dalal
Hi,
I'm currently facing one typical issue and looking for the solution for the
same.
We have a software development project activity. For some portion of the
tasks (like bug resolving etc) it is very difficult to judge the order of the
tasks, means person may have to work on multiple tasks as per the priorities.
For example, For one task, there are 3 sub-tasks - Task A (3 days), Task B
(2 Days) and Task C (2.5 Days). From this we can understand that total time
reqd would be 7.5 days and same resource is working on it. We are not aware
about the order in which he will carry out these tasks.
So if in Project, we will put dependencies, that will not give the real
scenario, same way if we will not do it then it will show that the main task
will be finished in 3 days (which is incorrect).
So is there any mechanism by using which, we can co-releate tasks and
estimate the excate completion date? What are the other options to create
this scenario using MS Project 2003 Server?
Thanking you in anticipation
I'm currently facing one typical issue and looking for the solution for the
same.
We have a software development project activity. For some portion of the
tasks (like bug resolving etc) it is very difficult to judge the order of the
tasks, means person may have to work on multiple tasks as per the priorities.
For example, For one task, there are 3 sub-tasks - Task A (3 days), Task B
(2 Days) and Task C (2.5 Days). From this we can understand that total time
reqd would be 7.5 days and same resource is working on it. We are not aware
about the order in which he will carry out these tasks.
So if in Project, we will put dependencies, that will not give the real
scenario, same way if we will not do it then it will show that the main task
will be finished in 3 days (which is incorrect).
So is there any mechanism by using which, we can co-releate tasks and
estimate the excate completion date? What are the other options to create
this scenario using MS Project 2003 Server?
Thanking you in anticipation