Dick:
The integration with Outlook in the 2003 version of the software working
with Project Server places the task assignments on the Calendar, not the
task list. They can be statused within the appointment dialog on a new tab
that is added. You can also display specific Project Server pages inside
Outlook using another integration approach that the system provides using
either a folder or an Outlook shortcut. This method puts nothing on the
calendar or in the task list.
Functional degradation occurs using older versions of Office against the new
SharePoint technologies. You can still use older versions of Outlook, but
some SharePoint functions will not be supported and others will work less
well.<g> This is purely related to the Office Web components.
--
Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com
For Project Server FAQs visit
http://www.projectserverexperts.com
For Project FAQs visit
http://www.mvps.org/project
-