J
JR
What I want to do is create multiple "what-if" scenarios that can be
visible all from the same file. The way it would work is the
following:
1) The logic would remain constant.
2) As usual, the logic and duration will determine the values for
Start and Finish fields.
3) For "what-if" scenario 1, I would enter an alternate duration into
the Duration1 field and the Start1 and Finish1 fields would be
calculated. Scenario 2 would use the Duration2, Start2, and Finish2
fields and so on.
Has this already been done? Is there some setting in Project that
already does this? If not, is there a macro that already does this?
Thank you!
JR
visible all from the same file. The way it would work is the
following:
1) The logic would remain constant.
2) As usual, the logic and duration will determine the values for
Start and Finish fields.
3) For "what-if" scenario 1, I would enter an alternate duration into
the Duration1 field and the Start1 and Finish1 fields would be
calculated. Scenario 2 would use the Duration2, Start2, and Finish2
fields and so on.
Has this already been done? Is there some setting in Project that
already does this? If not, is there a macro that already does this?
Thank you!
JR