Can you baseline a Proposal or Activity somewhere?

S

Shawn Ericsson

We are using Project Server 2007 w/ SP2 and the April CU update.

I asking if you can baseline a Proposal and Activity due to the fact that
the status indicator shows up black in Project Center after publishing.

I understand that you can uncheck showing the Proposals and Activities box
so it doesn't show them, but our organization would like them in there to
track.

Any suggestions would be greatly appriciated.

Thanks
Shawn Ericsson
 
D

Dale Howard [MVP]

Shawn --

No, it is not possible to save a Baseline for a Proposal or an Activity
Plan. Sorry.
 
S

Shawn Ericsson

Thanks a lot Dale - kind of figured since there aren't many options for them.
 
D

Dale Howard [MVP]

Shawn --

I have found both of these tools to be pretty cumbersome and not nearly
powerful enough for most organizations to use. The lack of Baseline
capabilities is one more strike against the usefulness of either tool. Hope
this helps.
 