We just upgraded from Project Server 2002 to 2003 and converted an existing
schedule over. We have resources reporting hours to the project monthly and
have dealt with 2002's issues relative to spreading actuals entered across
the entire month regardless of the start/finish date. Now, 2003 has the
"lock down actuals" functionality that requires resources to enter actuals by
day if the task is not planned across the entire month (you get a message
saying "you don not have any scheduled work during this week"). Since we're
nearing completion of the project (only months left of a multi-year effort),
we don't want to change approaches at this point. Is there any way to "turn
off" this lockdown actuals functionality in Project Server 2003 so that we
can continue reporting actuals by month regardless of the start date? Any
assistance would be appreciated.
schedule over. We have resources reporting hours to the project monthly and
have dealt with 2002's issues relative to spreading actuals entered across
the entire month regardless of the start/finish date. Now, 2003 has the
"lock down actuals" functionality that requires resources to enter actuals by
day if the task is not planned across the entire month (you get a message
saying "you don not have any scheduled work during this week"). Since we're
nearing completion of the project (only months left of a multi-year effort),
we don't want to change approaches at this point. Is there any way to "turn
off" this lockdown actuals functionality in Project Server 2003 so that we
can continue reporting actuals by month regardless of the start date? Any
assistance would be appreciated.