Can you set up "If then senarios within MS Projects"

J

Jan

I would like to setup a dynamic template with "If Then Senarios" . I know
about the taske dependencies, this is not what I am looking for. What I would
like to be able to do is IF a task is applicable THEN these are the tasks
that need to be completed. IF the task is not applicable THEN these are the
steps that would need to be created? is there anyway of doing this within one
template?
 
J

Jim Aksel

Please see my post from earlier today. I answered a very similar question
"How do I enter risks in a schedule".

--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top