Can you still actual hours in timesheets?

J

Joe

My users were tracking actuals using PWA. They would always be able to see
the actuals they entered in the past using the timesheet view. Today I
deleted the project plan from the server then put a copy of the same plan
back on the server. So I have all the actuals, but the users can no longer
see the past actuals anymore. I know it’s because I deleted the plan, then
put it back on the server. Can I get the past Actuals to be displayed in the
timesheets again? I have the data in the plan.
 
D

Dale Howard [MVP]

Joe --

Do the following:

1. Open the project
2. Click Collaborate - Publish - Republish Assignments
3. Select the "Overwrite actual work entered by resources" option
4. Click OK

Hope this helps.
 