Can you use Project for budget charts?

A

AM

I want to include budget without the hourly resource cost. Our project
budgets don't include the soft dollars that go into daily office work, but
treat that as a given.
Is there room on Project to have costs in fees for advertising and other
campaigns?
 
M

Mike Glen

Hi AM,

Welcome to this Microsoft Project newsgroup :)

If you View/Table:()/Cost you will see a Fixed Cost field designed just for
such a use.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 