Cancel reminders for certain tasks

C

Christina

I have a few tasks that I did not intend to publish to the resources'
timesheets. Now they are receving reminders that these tasks are overdue.
Is there a way that I can "cancel" the reminders but only for certain tasks?
I still want them to receive reminders for tasks that I did intend to
publish. The only other thing I can think of is to delete the task and
re-add it but I would prefer not to do that if there is a better way.

thank you!
Christina
 
G

Gary L. Chefetz [MVP]

Christina:

To remove the reminders, you need to close out the assignments and remove
the resources from the tasks. However, it sounds as though you had a
different outcome in mind. What did you intend for these tasks? Why would
you put resources on tasks that you don't expect them to update?

PS: You did a fine job answering Richard's question

--

Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com
 
C

Christina

Gary,

First let me apologize for my tardy reply. Busy, Busy, Busy :)

With respect to my odd question, although we strive to have an accurate
baseline in terms of task durations, start/ finish dates, anticipated work,
etc, we have several situations where the project is already underway before
the project schedule is finalized. (I know what you're saying in your
head.... it's a slow process to get everyone on board with the whole plan
first, act later philosophy)

Anyway, what happens is there are tasks that are assigned to resources that
are dependent on other tasks getting done. But until the predecessor tasks
are updated, the dates on the successor tasks may be inaccurate, causing
Overdue TAsk reminders to be sent to the resources that are waiting for
predecessor tasks to be completed. Does that make sense?

To avoid this, I had wanted to wait to publish the successor tasks until the
predecessors were complete, thus pushing the schedule forward to reflect a
more accurate representation of the project timeline. But I inadvertently
published the task assignments for the successor tasks.... so these task
owners started receiving reminders. Not wanting my resources to become
"desensitized" to these reminders, I turned them off completely. I thought
of removing the resources from the assignments and then re-adding them. But
since Project automatically generates a notice to the resource saying they
were taken off the task, I decided that would only add to the confusion.

Whew! I'm sorry this explanation is so long.... but I wanted to make sure
you understood our "unique" situation. That said, it sounds like outside of
removing the resources from the task and then re-adding them, an assignment
cannot be "unpublished", yes?

Oh well... I guess I will need to be more careful in the future :)

Thank you for your help!!! And I'm so glad you approve of my response to
Richard. I was hoping that I didn't say anything that would make the MVPs
cringe :)

Christina
 
G

Gary L. Chefetz [MVP]

Christina:

Hmmm. The best you could do in this situation, without completely removing
the plan and republishing it, is to use the Tracking function in Project to
move the uncompleted work forward to the status date. At least this way the
tasks won't show as late and the nasty notices go away. The notices are
based on current plan, not baseline.

--

Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com
 
C

Christina

Gary-

Now why didn't I think of that? That makes complete sense. I will give
that a try and see how things go.

As always, thank you so much for your help!

Have a great day :)
-Christina
 