If a project gets cancelled mid-stream, what is the best
way to represent it's cancellation within Project Server.
If possible, I would like to still be able to show the
assignments, but not have those assignments count toward a
resources allocation/assignment projections within Project
Server.
Is this possible?

Thanks,
Linda
 
D

Dale Howard [MVP]

Linda --

You might do something like this:

1. Select all of the uncompleted tasks in the project and change the
Remaining Work to 0 hours (this will "cancel" the uncompleted portion of
every task)
2. Add a note to every cancelled task to indicate when and why the task was
cancelled
3. In the Resource Sheet view of the project, change the Booking Type value
for every resource to Proposed
4. If you are using a custom Project field to indicate its current status,
set the value to Cancel
5. Save and republish the project

Just some thoughts. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top