Babar.Asif
Hi,
Every time I try to change the start date for a particular task, it
adds a constraint of Start No Earlier Than but doesn't change the start
date. Consider the following example
TASK 1
Start Date: 1/11/06
End Date: 1/11/06
Duration: 4hr
Predecessor: N/A
Now if I try to change the start date to 1/9/06, it doesn't change the
date but just adds the No Earlier Than constraint.
Any reasons why Project would do that?
Thanks.
Babar