In MS Project 2003, one of the PM in our team is unable to remove ent.
resources from the Summary level task (they are added by mistake) though
there are no actuals reported by team members for the tasks underneath. It
returns following message:
"Cannot delete or reassign tasks or assignments with Protected actuals"
We have setup Project Server 2003 with following:
a) Time Period Settings: - Managed Periods - Allow only Project Web Access
users to update actuals during open periods.
b) Managed Timesheet Periods: - Open timesheet Periods (7/1/07 to 12/31/07)
c) Summary Task where PM wants to remove resources from spans from 9/3/07 to
10/05/07 with no Actual Start and Actual Finish = NA
How to resolve this issue...
Thanks in advance
Kishore.
resources from the Summary level task (they are added by mistake) though
there are no actuals reported by team members for the tasks underneath. It
returns following message:
"Cannot delete or reassign tasks or assignments with Protected actuals"
We have setup Project Server 2003 with following:
a) Time Period Settings: - Managed Periods - Allow only Project Web Access
users to update actuals during open periods.
b) Managed Timesheet Periods: - Open timesheet Periods (7/1/07 to 12/31/07)
c) Summary Task where PM wants to remove resources from spans from 9/3/07 to
10/05/07 with no Actual Start and Actual Finish = NA
How to resolve this issue...