M
Mark Etheridge
Hello,
We are trying to implement EPMS and so I have added a project to the project
server 2003 (EPMSimplement.mpp). I have been configuring the settings within
EPMS. One problem that I am having is that we cannot enter in 'Actuals' in
timesheet view. We can only adjust the % complete, and remaining work
columns. I have been adjusting the setting within the "Customize Probject
Web Access" within the Admin center. I have tried all options, including the
'Managed Periods' option where you open reporting periods. Nothing seems to
work with this project. This project file was added to project server when
the project was 50% complete. So there are no actuals added for the first
half of the tasks. Would this have something to do with my problem? Does
anyone have any options that I can try to hopefully resolve?
I have added a few other 'dummy' projects, and we can enter 'actuals' to the
tasks from these projects.
Mark
We are trying to implement EPMS and so I have added a project to the project
server 2003 (EPMSimplement.mpp). I have been configuring the settings within
EPMS. One problem that I am having is that we cannot enter in 'Actuals' in
timesheet view. We can only adjust the % complete, and remaining work
columns. I have been adjusting the setting within the "Customize Probject
Web Access" within the Admin center. I have tried all options, including the
'Managed Periods' option where you open reporting periods. Nothing seems to
work with this project. This project file was added to project server when
the project was 50% complete. So there are no actuals added for the first
half of the tasks. Would this have something to do with my problem? Does
anyone have any options that I can try to hopefully resolve?
I have added a few other 'dummy' projects, and we can enter 'actuals' to the
tasks from these projects.
Mark