B
Bill Cole
Using PS and PWA 2007.
When entering time in PWA in the "My Tasks" screen, I want the resources to
be able to click on the Progress cell for their tasks and to see
the popup window which allows them to enter Actual Work for each period.
This used to work for my published project.
At some point I noticed that the little popup window no longer appears when
the resources click on the Progress cell for their tasks. They can
manually edit the progress number, but this is awkward and there is no way
of indicating which week they want to apply the hours for.
I created a new test project and published it to Project Server and I
noticed the behavior for this new project is the way I want it.
If I click on the Progress cell for any tasks, I do get the popup window
allowing me to enter actual hours for any period I navigate to.
I also noticed that in the new project I get more data in the Progress
column. The format is as follows: "1d of 4d (25%)" If I hover over the
cell,
I get the hint "Click here to edit timephased actuals". For the project
where this is no longer working, the status in the Progress column is "1d"
and no hint is shown if you hover above that cell.
I am guessing some server or project setting got changed so that previously
published project no longer work the way I want, but newly published
projects do. Does anyone have an idea of which setting causes this
behavior? Also, how do I fix projects already published to again allow
the
resources to enter actual hours via the popup window?
Also, is there any way to have the Progress and Remaining Work columns show
totals in terms of HOURS instead of DAYS? The popup window
allows you to enter actuals in terms if HOURS, but the totals on the main
screen are in terms of DAYS.
Thanks,
Bill Cole
When entering time in PWA in the "My Tasks" screen, I want the resources to
be able to click on the Progress cell for their tasks and to see
the popup window which allows them to enter Actual Work for each period.
This used to work for my published project.
At some point I noticed that the little popup window no longer appears when
the resources click on the Progress cell for their tasks. They can
manually edit the progress number, but this is awkward and there is no way
of indicating which week they want to apply the hours for.
I created a new test project and published it to Project Server and I
noticed the behavior for this new project is the way I want it.
If I click on the Progress cell for any tasks, I do get the popup window
allowing me to enter actual hours for any period I navigate to.
I also noticed that in the new project I get more data in the Progress
column. The format is as follows: "1d of 4d (25%)" If I hover over the
cell,
I get the hint "Click here to edit timephased actuals". For the project
where this is no longer working, the status in the Progress column is "1d"
and no hint is shown if you hover above that cell.
I am guessing some server or project setting got changed so that previously
published project no longer work the way I want, but newly published
projects do. Does anyone have an idea of which setting causes this
behavior? Also, how do I fix projects already published to again allow
the
resources to enter actual hours via the popup window?
Also, is there any way to have the Progress and Remaining Work columns show
totals in terms of HOURS instead of DAYS? The popup window
allows you to enter actuals in terms if HOURS, but the totals on the main
screen are in terms of DAYS.
Thanks,
Bill Cole