J
JustMe
Hi all,
I have created task1, task2 to the same resource R with 100% on each
task within the same period of time.
I would expect the resource to be overloaded with 200% but MS Project
force the tasks to be done at separate times. It doesn't matter how I
set the task type as Fixed Unit, Duration or Fix Work. MS Project
doesn't allow me to change the Start date to start both tasks at the
same time.
Of course it will work if I reduce the resource R to 50%, but that's
not my intention.
Can someone explain to me this behavior, or any way to get around it?
Thanks a bunch.
Regards,
Frank
I have created task1, task2 to the same resource R with 100% on each
task within the same period of time.
I would expect the resource to be overloaded with 200% but MS Project
force the tasks to be done at separate times. It doesn't matter how I
set the task type as Fixed Unit, Duration or Fix Work. MS Project
doesn't allow me to change the Start date to start both tasks at the
same time.
Of course it will work if I reduce the resource R to 50%, but that's
not my intention.
Can someone explain to me this behavior, or any way to get around it?
Thanks a bunch.
Regards,
Frank