C
Christina
MS Project 2003, Project SErver 2003
Just when I thought I understood the nuances of when/ how to remove a
resource from a task, I experience a situation that has me thoroughly
stumped. This is long but I wanted to be very thorough.
Situation:
I have a task that has 2 resources assigned to it.
Duration = 1 day
Work = 1 hour
Task was set to Fixed Units, Effort Driven
Resources are each 50% allocated to the task, therefore scheduled for .5
hours each.
I find out that the work was completed by one resource (in .5 hours) and the
second resource is not needed. Therefore, my plan was to remove the
unnecessary resource from this task. The first resource had submitted her
update and it was approved, reflecting her assigned was 100% complete and the
task as 50% complete. The second person had not entered anything at all and
was showing as 0% complete.
What I did:
Open project and go to Task Usage View
Zeroed out remaining work for the 2nd resource (noticed that % Work Complete
was 100%, not 0% as I would have expected)
Republished only his assignment and overwrote work entered by him (he had
not entered any updates at all).
Selected the task and clicked on Tools/ Assign Resources to select the
resource I wanted to remove
Received a message saying that there are already actuals associated with
this task and did I really want to delete them.
Confused, I said No and just left the second resource assigned to the task
with 0 work assigned. Since the first resource had completed all of the work
for the task, the task shows as complete.
My question is: Why did the task say there were actuals reported when I
tried to remove just the resource that did no work (and absolutely did not
update anything in their timesheet)? Is it because there were actuals
reported by another resource and their work was considered "complete"? And
since the task had been effort driven, Project would have wanted to assign
the 2nd resource's work to the first?
I ran into this same situation with a task that had 3 people assigned. Also
effort driven. Tried to zero out one resource's assignment. The 2nd
resource was complete and the 3rd had no actuals reported yet. After zeroing
out the 1st resources's RW, I tried to remove them from the task and noticed
that project was also asking me how I wanted to divide up the remaining work.
I said to reduce work since the task required less resources. I then
received the same message about actuals already being reported and did I want
to delete them. I said no. The resource I removed from the task
re-appeared. I republished the task and noticed that the resource I had
initially removed and subsequently re-appeared was now receiving a new
assignment.
Please help me to understand this behavior. I am creating internal
procedures for PMs and need to be able to explain why this is happening.
Thank you in advance!
Christina
Just when I thought I understood the nuances of when/ how to remove a
resource from a task, I experience a situation that has me thoroughly
stumped. This is long but I wanted to be very thorough.
Situation:
I have a task that has 2 resources assigned to it.
Duration = 1 day
Work = 1 hour
Task was set to Fixed Units, Effort Driven
Resources are each 50% allocated to the task, therefore scheduled for .5
hours each.
I find out that the work was completed by one resource (in .5 hours) and the
second resource is not needed. Therefore, my plan was to remove the
unnecessary resource from this task. The first resource had submitted her
update and it was approved, reflecting her assigned was 100% complete and the
task as 50% complete. The second person had not entered anything at all and
was showing as 0% complete.
What I did:
Open project and go to Task Usage View
Zeroed out remaining work for the 2nd resource (noticed that % Work Complete
was 100%, not 0% as I would have expected)
Republished only his assignment and overwrote work entered by him (he had
not entered any updates at all).
Selected the task and clicked on Tools/ Assign Resources to select the
resource I wanted to remove
Received a message saying that there are already actuals associated with
this task and did I really want to delete them.
Confused, I said No and just left the second resource assigned to the task
with 0 work assigned. Since the first resource had completed all of the work
for the task, the task shows as complete.
My question is: Why did the task say there were actuals reported when I
tried to remove just the resource that did no work (and absolutely did not
update anything in their timesheet)? Is it because there were actuals
reported by another resource and their work was considered "complete"? And
since the task had been effort driven, Project would have wanted to assign
the 2nd resource's work to the first?
I ran into this same situation with a task that had 3 people assigned. Also
effort driven. Tried to zero out one resource's assignment. The 2nd
resource was complete and the 3rd had no actuals reported yet. After zeroing
out the 1st resources's RW, I tried to remove them from the task and noticed
that project was also asking me how I wanted to divide up the remaining work.
I said to reduce work since the task required less resources. I then
received the same message about actuals already being reported and did I want
to delete them. I said no. The resource I removed from the task
re-appeared. I republished the task and noticed that the resource I had
initially removed and subsequently re-appeared was now receiving a new
assignment.
Please help me to understand this behavior. I am creating internal
procedures for PMs and need to be able to explain why this is happening.
Thank you in advance!
Christina