R
Ruth Halbach
I have seen in previous responses from Dale where he suggests the following
steps...
1. Team members enter time on their My Timesheet on a daily basis and save
the changes.
2. On the last day of the reporting period, submit the timesheet to the
Timesheet approver.
3. On the My Tasks page, import the My Timesheet information.
4. Adjust the Remaining Work, if necessary.
5. Add a Note as needed.
6. Submit the task progress to the project manager.
This is exactly what we are trying to do, however, remaining work does not
allow update. On the task page, in timesheet view, we can see % work
complete, remaining work, start, finish, actual work, and progress after we
import the timesheet. None of the fields are input capable. If I click on
the task name to see the detail, again, none of the fields are input capable.
Is there a setting that I've missed?
steps...
1. Team members enter time on their My Timesheet on a daily basis and save
the changes.
2. On the last day of the reporting period, submit the timesheet to the
Timesheet approver.
3. On the My Tasks page, import the My Timesheet information.
4. Adjust the Remaining Work, if necessary.
5. Add a Note as needed.
6. Submit the task progress to the project manager.
This is exactly what we are trying to do, however, remaining work does not
allow update. On the task page, in timesheet view, we can see % work
complete, remaining work, start, finish, actual work, and progress after we
import the timesheet. None of the fields are input capable. If I click on
the task name to see the detail, again, none of the fields are input capable.
Is there a setting that I've missed?