D
Dave Barr
I have a master schedule with multiple (6) inserted schedules. Between these
schedules I have several external dependencies defined - one example being a
dependency in the Test schedule that says that test shouldn't start until
Engineering is complete (a task in another schedule). This is largely
working but I have one specific external dependency that doesn't work.
In my master schedule I create an external depenency in one sub project to a
task in another sub project and then when I hit OK it recognizes that it is
a valid external dependency but doesn't update the Start Date to reflect the
completion of the External Dependancy (Note that I have my Contsraint Type
set to As Soon as Possible so that shouldn't affect things)
Added to this 2 other things are strange:
1) When I edit the task and try and change the dependency it won't let me.
The box isn't greyed out but I can't make any changes to it (I can't even
delete it)
2) A task number abobe this seems to be missing. I have Task 21 which is a
summary task and then Task 23 which is the task I am having problems with
but no Task 22.
Any ideas on whether I am doing something wrong?
Thanks
Dave
schedules I have several external dependencies defined - one example being a
dependency in the Test schedule that says that test shouldn't start until
Engineering is complete (a task in another schedule). This is largely
working but I have one specific external dependency that doesn't work.
In my master schedule I create an external depenency in one sub project to a
task in another sub project and then when I hit OK it recognizes that it is
a valid external dependency but doesn't update the Start Date to reflect the
completion of the External Dependancy (Note that I have my Contsraint Type
set to As Soon as Possible so that shouldn't affect things)
Added to this 2 other things are strange:
1) When I edit the task and try and change the dependency it won't let me.
The box isn't greyed out but I can't make any changes to it (I can't even
delete it)
2) A task number abobe this seems to be missing. I have Task 21 which is a
summary task and then Task 23 which is the task I am having problems with
but no Task 22.
Any ideas on whether I am doing something wrong?
Thanks
Dave