Running Project Server 2003 sp2A
Using managed time periods
I have a project where the resource manager updated actuals on a task for a
resource. He zero-ed out all reported time for a task and moved to a
different task. After updating in project plan, the resource manager tried
to delete the the resource off the task but actual protected work was never
blanked out. When I try to update actuals via PWA no time appears. When I
look in the plan for the same time period, protected actual work exists.
When I sync to actuals, nothing happens in the plan. How do I fix this?
How did this happen?
Thank you in advance for your help.
Using managed time periods
I have a project where the resource manager updated actuals on a task for a
resource. He zero-ed out all reported time for a task and moved to a
different task. After updating in project plan, the resource manager tried
to delete the the resource off the task but actual protected work was never
blanked out. When I try to update actuals via PWA no time appears. When I
look in the plan for the same time period, protected actual work exists.
When I sync to actuals, nothing happens in the plan. How do I fix this?
How did this happen?
Thank you in advance for your help.