We are using Project Server 2003, we are using the timesheet view and
updating progress entering actuals and remaining work. We are also trying to
include a best forecast date for resources to populate in the timesheet view.
I have created and published and enterprise task date field calling it BFCD
and added it to the timesheet view..but the field is shaded yellow and the
resources can't edit it. The allow edit check box is checked when publishing
the field... is there something I am missing here? It doesn't help that they
can only see the field and not enter a date...
Any help would be appreciated..thx
Ellen
updating progress entering actuals and remaining work. We are also trying to
include a best forecast date for resources to populate in the timesheet view.
I have created and published and enterprise task date field calling it BFCD
and added it to the timesheet view..but the field is shaded yellow and the
resources can't edit it. The allow edit check box is checked when publishing
the field... is there something I am missing here? It doesn't help that they
can only see the field and not enter a date...
Any help would be appreciated..thx