P
pepe
Hi,
I have set-up my very first project plan. I created the tasks, assigned the
tasks to three developers including myself (the three of us are "team
members"). I published the project plan to project server.
When I open project web access I'm able to only see the tasks that I have
assigned to myself, which is ok, my problem is that we (myself and the other
two developers) are not able to enter the number of hours we have worked on a
task in the "Actual work" column, because for some reason it is disabled. For
some reason the only columns that are enable are the "% Work complete" and
the "Remaining work".
In the admin options of project web access (customize project web access), I
have set up the following options:
1. reporting progress as "hours of work done per day or per week..."
2. lock down defaults as " force project managers to use the progress..."
3. time period settings as "non managed periods - allow project and pwa
users to update actuals"
4. "resources should report their hours worked every day"
How can I make so that the "Actual work" column is enabled in the tiumesheet
view. I've been playing with the admin options for awhile but I'm not able to
figure it out.
Thanks.
I have set-up my very first project plan. I created the tasks, assigned the
tasks to three developers including myself (the three of us are "team
members"). I published the project plan to project server.
When I open project web access I'm able to only see the tasks that I have
assigned to myself, which is ok, my problem is that we (myself and the other
two developers) are not able to enter the number of hours we have worked on a
task in the "Actual work" column, because for some reason it is disabled. For
some reason the only columns that are enable are the "% Work complete" and
the "Remaining work".
In the admin options of project web access (customize project web access), I
have set up the following options:
1. reporting progress as "hours of work done per day or per week..."
2. lock down defaults as " force project managers to use the progress..."
3. time period settings as "non managed periods - allow project and pwa
users to update actuals"
4. "resources should report their hours worked every day"
How can I make so that the "Actual work" column is enabled in the tiumesheet
view. I've been playing with the admin options for awhile but I'm not able to
figure it out.
Thanks.