We just migrated from 03 to 07 and we have several migrated projects that
resources are unable to enter time against any of the tasks. We can get into
the cell but can't type anything.

Anyone know how to fix???
 
R

Reid McTaggart

Perhaps the statusing method for those projects does not allow the type of
entry you are trying to do? For example, if they are set to percent
complete, you would not be able to enter daily actual hours.

Just a guess....
 
R

Robert

I have seen this before when a client changed thier tracking method in PWA
and had not republished the project plans. After republishing the plans they
were then able to enter hours into the My Tasks.


--
Project Consultant

REJ Company

(e-mail address removed)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top