When I create a test task in Project Professional, using default parameters
and then indicate actual working hours.
Example
task for 2 days
normal workin hours is 8 hours
I work 10 hours 2 days and 10 hours on third day.
I recieve a very strange picture:
1. In the view Ghant Diagramm I see a break in may task - between first 2
days and third day. Nevertheless the data of beginning is 1sr, data of end is
3rd.
2. Duration of task is 2,75. Why???? At whole I have worked 30 hours and I
have indicated this.